The Region C Water Planning Group’s 7th multi-year planning cycle is now officially underway, after the Planning Group held its regular public meeting and a pre-planning meeting for the new planning cycle on Monday, October 19, 2026. This round of regional water planning will ultimately produce the 2031 Region C Water Plan, which will become part of the 2032 State Water Plan.
During its regular meeting, the Planning Group elected or re-elected a handful of voting members, including the addition of Nicholas Konen to represent the Industry interest group, replacing former Planning Group Vice Chair Russell Laughlin, who did not stand for reelection. The Planning Group also received nominations for and elected new officers: Chair Dan Buhman, Vice Chair Jenna Covington and Secretary Steve Mundt.
The Planning Group discussed proposals received and authorized the Trinity River Authority, Region C’s administrative agent, to enter into a contract with Freese and Nichols to serve as the Planning Group’s technical consultant for the new planning cycle. Freese has served in this capacity for Region C ever since the first regional water planning cycle in the late 1990s.
After adjournment for the pre-planning meeting, Freese presented to the Planning Group on the planning process and key milestones for the current cycle. Those milestones include the following:
- In 2027, the Planning Group will be receiving preliminary population and water demand projections from the Texas Water Development Board (TWDB) and preparing input to the TWDB on potential revisions to those projections, based on regional stakeholder feedback. This input and requests for specific changes are due to the TWDB in December 2027.
- Final population and demand projections will be adopted by the TWDB and sent to the Planning Group by April 2028, which will help determine the overall water need (supply/demand gap) that must be met through various recommended Water Management Strategies in the 2031 Region C Water Plan.
- Region C’s Technical Memorandum will be due to the TWDB no later than Nov. 10, 2028. This is a key mid-point deliverable documenting population and water demand projections, water availability and existing supplies, an analysis of water needs, and identification of potentially feasible Water Management Strategies (WMS’s) that may be included as recommended or alternative strategies in the final Regional Water Plan.
- Region C’s Initially Prepared Plan (IPP, the draft version of Region C’s 2031 Water Plan) will be due to the TWDB by March 4, 2030.
- After receiving and considering public and agency input on the IPP, the Planning Group must adopt and submit a final 2031 Region C Water Plan to the TWDB by October 21, 2030.
- The Region C Water Plan, along with other regions’ plans, will be reviewed and consolidated by the TWDB into the 2032 State Water Plan.
The Planning Group also heard comments from several members of the public about the 7th planning cycle, including input on the need for interregional coordination with Region I, population projection concerns involving the City of Celina and a general statement of support for the regional water planning process.
Next, Freese presented an overview of the potential process for interregional coordination throughout the current planning cycle.
Upon closing the pre-planning meeting, the regular meeting continued with an update from the Interregional Working Group formed as a result of the 2025 mediation agreement between Regions C and D. They reported that a consultant, Hazen, has been selected to conduct the joint study on the potential impacts and benefits of the proposed Marvin Nichols Reservoir, and contracting is expected to be completed in late October, so the consultant’s work on the joint study can begin in November 2026. The study is expected to take approximately 15 months. Next steps will include identifying up to 12 key stakeholders from each region whose input will be received and evaluated as part of the joint study process.
The Interregional Working Group also reported that the Region C “apples to apples” comparative study of Marvin Nichols and Toledo Bend is currently on hold, pending the development of joint study results that will be useful for efficient completion of the comparative study.
Members of the public wishing to stay abreast of upcoming Planning Group meetings and public involvement opportunities throughout the planning cycle should monitor the Region C website, subscribe to Region C e-notifications (using the sign-up form on the website), or email info@regioncwater.org for more information. Thank you for your interest in Region C Water Planning!