Planning Milestones

Planning milestones for development of the 2026 Region C Water Plan
include the following:

2021

Milestone Icon

August 31, 2021

Initial planning contract execution deadline

Milestone Icon

November 1, 2021

Region C WPG pre-planning meeting

2022

Milestone Icon

January 2022

TWDB releases draft non-municipal demand projections

2023

Milestone Icon

February 2023

Draft population and municipal demand projections released by the TWDB

Milestone Icon

August 2023 – October 2024

Identification of potentially feasible Water Management Strategies

2024

Milestone Icon

March 3, 2024

Interregional Planning Council report due to the TWDB

Milestone Icon

March 4, 2024

Technical Memorandum due to the TWDB

2025

Milestone Icon

March 3, 2025

Initially Prepared (draft) Regional Water Plan due to the TWDB

Milestone Icon

Summer 2025

Public hearing on the Initially Prepared Regional Water Plan

Milestone Icon

October 20, 2025

Final Regional Water Plan due to the TWDB